Sample questions
You've seen the pattern — here are a few of the actual PYQs.
ESE2025
Which one of the following float of an activity is the spare time available for that activity, if that activity is started as late as possible and is finished as early as possible?
- A Total float
- B Independent float
- C Free float
- D Slack
Answer key not yet available (pending official release)
Engineering › Engineering Mathematics & General
ESE2022
In Network Computation Process, which one of the following is correct for forward pass ?
- A It starts with the first project activity(ies) and traces each path (c hain of sequential activities) through the network to the last project activity(ies) ✓
- B This is the longest path in the network, which will delay the project
- C It starts with the last project activity(ies) on the network
- D It starts with the last project activity(ies) and traces each path (c hain of sequential activities) through the network to the first project activity(ies)
✓ Correct answer: (A)
Management & Industrial Relations › Principles of Management
Study how UPSC repeats — not just the papers
₹199 / 1 year · Founding Member
Full access unlocks the three things no PYQ PDF gives you:
① Cross-exam learning — see the same idea recur across CSE, CAPF, CDS and NDA.
② Topic evolution — how each idea is framed, year by year.
③ Question intelligence — every PYQ + answer, linked to related concepts and similar questions.
e.g. Round Table Conference: CDS 2017 → CSE 2017 → … → CAPF 2024
15 days free, no card required — then ₹199 for 1 year.
Start your 15-day free trial →